Appendix
264 of 268 Solar-Log
1000/500/200
Installation
Interconnection of Kaco Powador inverters
Figure 16: Interconnection of Kaco Powador inverters
Instructions for Powador 6400xi and 8000xi
Interconnection of Powador 6400Xi and 8000xi:
Set 1 inverter as Master, 2 as Slaves;
Read the labelling on the inverter circuit board!
Clamp the Solar-Log™ data cable to theLOGGER terminal strip on the
Master inverter
Also connect the inverters to each other through the SYM terminal strip
Connect any additional inverters through the Logger terminal strip
On the inverter operating display: Set the communication addresses,
numbering consecutively
On the inverter operating display: Switch SYM Bus to active
Powador 6400Xi and 8000xi stand-alone mode:
Set the inverter to Slave, irrespective of labelling on the circuit board
Clamp the Solar-Log™ data cable to the SYM Bus terminal strip
On the inverter operating display: Switch SYM Bus to inactive
On the inverter operating display:
Set the communication addresses, numbering consecutively