1. Introduction
1.1. Introduction
This manual provides information on functionality and maintenance of the TripleLynx CN solar
inverter.
The inverter display and Web Server are available in Chinese language only. In the manual,
English texts appearing in the screenshots and menus are shown for guidance only.
Illustration 1.1: TripleLynx CN 8 kW, 10 kW, 12.5 kW, 15 kW
CGC marking - This certifies the conformity of the equipment with the regu-
lations which apply in accordance with China General Certification Center,
CGC/GF004:2011.
1.2. Operation Mode Definition
Off grid (LEDs off)
When no power has been delivered to the AC grid for more than 10 minutes, the inverter dis-
connects from the grid and shuts down. This is the normal night mode. The user and communi-
cation interfaces are still powered for communication purposes.
Connecting (Green LED flashing)
The inverter starts up when the PV input voltage reaches 250 V. The inverter performs a series
of internal self-tests, including PV auto detection and measurement of the resistance between
the PV arrays and earth. Meanwhile, it also monitors the grid parameters. When the grid pa-
rameters have been within the specifications for the required amount of time (depends on grid
code), the inverter starts to energise the grid.
On grid (Green LED on)
The inverter is connected to the grid and energises the grid. The inverter disconnects if: It de-
tects abnormal grid conditions (depending on grid code), if an internal event occurs or if no PV